Date Filed | Summary | Pages |
05/02/2006 | Memo with attached final inspection report and closing case of record, filed by Railroad Section-PUCO. | 6 |
08/29/2005 | Field and office report and construction authorization letter to NS, filed by PUCO staff. | 3 |
08/23/2005 | Plan, cost estimate and material list filed in the Railroad Division by B. Sykes on behalf Norfolk Southern Corporation. | 1 |
06/08/2005 | Entry ordered that; the subsidy stipulation adopted and approved that; by September 6, 2005, NS submit to the Commission's Railroad Division site plans and cost estimates for these projects that; by September 13, 2005, NS file a letter in this docket advising that it has submitted plans and cost estimates to the Commission, that; following approval of the site plans and cost estimates, NS proceed with and complete the project on or before June 8, 2006, that; NS follow the detailed instructions as outlined in the letter of construction authorization, that; NS notify the Commission 30 days before the projected date of completion, that; at the time the staff makes its final inspection and finds that the installation is completed and has been in service, staff will file a memorandum in this docket directing the Docketing Division to close this case of record. | 4 |
06/08/2005 | Service Notice | 1 |
05/27/2005 | In the matter of the application of Norfolk Southern Railway Company request for the installation of active warning devices at the Norfolk Southern grade crossing on East Highland Ave./CR111 (524-360W), Summit County. | 12 |
|