DIS - Case Record for 04-1768-EL-BLN Skip to main content

Case Record For:

04-1768-EL-BLN

Case Title: FIRSTENERGY/OTTAWA-WEST FREMONT NO.1 & 2
Status: AR-Archived
Industry Code: EL-ELECTRIC
Purpose Code: BLN-letter of notification
Date Opened: 11/23/2004
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
01/15/2008Correspondence stating that each of these projects was a transmission upgrade related to the installation of the West Fremont Energy Center, the work on three of these projects was completed and the last of the construction has been completed but the letter of notification was inadvertently omitted filed on behalf of FirstEnergy Service Company by T. Krauss.1
09/23/2005Letter stating that project is scheduled to begin on September 12, 2005 but may be delayed because the FirstEnergy crews assigned to this project on assisting with the Hurricane Katrina recovery efforts, filed by T. Kraus.1
05/10/2005Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss.3
12/30/2004Staff investigation Report and Recommendation filed by the OEPA.2
11/23/2004In the matter of the Letter of Notification, Ottawa-West Fremont No.1 & No. 2 138 kV Transmission Lines Reconductoring Project.69