01/15/2008
|
Correspondence stating that each of these projects was a transmission upgrade related to the installation of the West Fremont Energy Center, the work on three of these projects was completed and the last of the construction has been completed but the letter of notification was inadvertently omitted filed on behalf of FirstEnergy Service Company by T. Krauss. |
09/23/2005
|
Letter stating that project is scheduled to begin on September 12, 2005 but may be delayed because the FirstEnergy crews assigned to this project on assisting with the Hurricane Katrina recovery efforts, filed by T. Kraus. |
05/10/2005
|
Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss. |
12/30/2004
|
Staff investigation Report and Recommendation filed by the OEPA. |
11/23/2004
|
In the matter of the Letter of Notification, Ottawa-West Fremont No.1 & No. 2 138 kV Transmission Lines Reconductoring Project. |