Date Filed | Summary | Pages |
06/14/2005 | Notification of project completion filed by S. Lane on behalf of The Cincinnati Gas and Electric Company. | 1 |
02/01/2005 | Letter serving as notification that CG&E had a pre-construction meeting on Friday, January 21, 2005 filed by S. Lane. | 1 |
10/25/2004 | Staff investigation report and recommendation filed by PUCO staff. | 1 |
09/14/2004 | In the matter of the letter of notification regarding a Cincinnati Gas & Electric Company project, Beckjord-Silver Grove 138kV Transmission line. | 47 |
|