06/22/2004 | Letter informing Commission that project was completed on 6/7/04, filed on behalf of applicant by T. Krauss. | 1 |
05/04/2004 | Letter to Mr. Lambeck notifying that the start of construction was slightly delayed beyond due date, and is expected to begin on approximately May 6, 2004, notification will be made when project is completed, filed on behalf of applicant by T. Krauss. | 1 |
02/24/2004 | Staff investigation report and recommendation for the West Akron-West Medina #1 Transmission Line Tap to Buckeye Substation project. | 1 |
01/15/2004 | In the matter of the application of American Transmission Systems, Inc. to the State of Ohio Power Siting Board for the West Akron-West Medina #1, 138kV Transmission Line Tap to Buckeye Substation. | 37 |
|