Date Filed | Summary | Pages |
01/17/2008 | Semi-annual monitoring report for the Millers Creek site representing the fourth and final report in the second series of two-year monitoring reports, filed by S. Lane on behalf of Duke Energy. | 4 |
06/18/2007 | Semi-annual monitoring report for the Millers Creek site in compliance with restoration and planting plan, inspected on March 20, 2007 and again on June 3, 2007 filed by S. Lane on behalf of Duke Energy. | 3 |
07/26/2006 | Semi annual monitoring report for the Millers Creek site filed by S. Lane on behalf of Duke Energy. | 3 |
12/07/2005 | Letter stating that the staff has reviewed and accepted the proposed plan for the restoration of the Miller's Creek crossing which was inadvertently cleared by CG&E maintenance personnel and to notify the staff upon the commencement of the planting activity filed by K. Lambeck on behalf of Power Siting Board. | 1 |
12/07/2005 | Letter stating that CG&E will replant the woody species that were moved by mistake and they have taken the steps necessary to see that does not happen again filed by S. Lane and R. McElfresh. | 4 |
12/07/2005 | Letter submitting the third monitoring report in compliance with plan filed by R. McElfresh on behalf of Cincinnati Gas & Electric Company. | 3 |
11/22/2004 | Millers Creek Restoration Plan filed by R. McElfresh on behalf of Cincinnati Gas & Electric Company. | 3 |
02/23/2004 | Correspondence informing that construction was complete on November 14,2003 and put into commercial use December 5,2003. filed on behalf of applicant by R. McElfresh. | 1 |
12/11/2003 | Response to request for a brief summary of the actions that CG&E has taken to repair erosion and sedimentation controls at a few locations along a route of the C 314 natural gas pipeline filed on behalf of applicant by R. Elfresh. | 4 |
11/28/2003 | Restoration report plan, filed on behalf of CG&E by R. McElfresh. | 3 |
08/22/2003 | Synopsis of the measures taken to enhance the internal communications with contractors, filed on behalf of applicant by R. McElfresh. | 2 |
08/01/2003 | Letter to Mr. O'Dell of PUCO staff, filed on behalf of Cinergy by R. McElfresh. | 20 |
08/01/2003 | Letter to Mr. McElfresh, filed on behalf Ohio Power Siting Board by K.Lambeck. | 2 |
07/31/2003 | Investigation report filed on behalf of the PUCO staff by J. O'Dell. | 1 |
07/21/2003 | Investigation report, filed on behalf of Cincinnati Gas & Electric Company by J. O'Dell, B. Shakya & S. Malone of the PUCO staff. | 2 |