Date Filed | Summary | Pages |
07/09/2002 | Response to Letter of Notification, filed on behalf of applicant by T. Krauss. | 1 |
03/21/2001 | Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. | 1 |
03/21/2001 | Response to Letter of Notification, filed by K. Lambeck, PUCO staff. | 1 |
02/20/2001 | Federal Aviation Administration Aeronautical Studies filed on behalf of applicant by T. Krauss. | 11 |
01/30/2001 | In the matter of the Letter of Notification of American Transmission Systems, Inc. a subsidiary of FirstEnergy Corp., Fowles Group #17 and #18 138 kV Transmission Line Tap and Underground Circuit Project for service to the New MS-2 Substation at the Cleveland Hopkins International Airport. | 33 |
|