Case Record For:

00-1527-EL-BGN

Case Title: FREMONT ENERGY CENTER/SANDUSKY OH
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BGN-Application for a certificate/ generating station
Date Opened: 8/21/2000
Date Closed: 3/24/2015
Printable Docket Card Service List
View per page
Date FiledSummaryPages
03/24/2015Memo closing case with an effective date of 3/24/15.1
02/23/2012Notice of compliance filed by S. Doran on behalf of American Municipal Power, Inc..2
07/27/2011Service Notice2
07/25/2011Service Notice4
07/25/2011Entry ordered that the joint application to transfer the certificate from FirstEnergy to AMP be granted; that as a result of this transfer,AMP shall be bound by and comply with all terms and conditions of this certificate. 3
06/24/2011Letter in support of joint application to transfer a certificate to American Municipal Power filed by C. Schraff on behalf of FirstEnergy Generation Corp. 3
06/23/2011Notice of service of local government officials filed by R. Schmidt, Jr. on behalf of FirstEnergy Generation Corp.9
05/25/2011Amended Joint Application to Transfer a Certificate to American Municipal Power, Inc. filed by R. Schmidt, Jr. of FirstEnergy Generation Corp. and S. Doran of American Municipal Power, Inc.5
05/23/2011Joint Application of FirstEnergy Generation Corp and American Municipal Power, Inc. to transfer a certificate to American Municipal Power, Inc. filed by R. Schmidt, Jr. and Scott M. Doran on behalf of FirstEnergy Generation Corp and American Municipal Power, Inc.5
03/04/2008Service Notice4
03/03/2008Entry ordering that the application to transfer the certificate of environmental compatibility and public need for the construction and operation of the 704-MW electric generating station in Fremont, Sandusky County, Ohio from Calpine to FirstEnergy Generation Corp. is granted upon terms set forth in finding (5). (OPSB)3
02/15/2008Amended joint application to transfer a certificate to FirstEnergy Generation Corp. filed on behalf of Calpine Corporation, Inc and FirstEnergy Generation Corp. by S. Bloomfield and C. Schraff. 2
02/11/2008Joint application of Fremont Energy Center LLC and FirstEnergy Generation Corp.to transfer certificate filed on behalf of FirstEnergy Generation Corp. by S. Bloomfield and C. Schraff. 3
12/22/2006Report on construction activity for year 2006, filed on behalf of Fremont Energy Center by K. Florence.1
06/02/2005Annual progress report of Fremont Energy Center Construction filed by J. Garvey.2
01/13/2005Service Notice2
01/10/2005Entry approving the joint application of Calpine and ATSI permitting ATSI to assume the obligations of the certificate conditions related ti the Fremont Energy Center switchyard.3
11/16/2004Staff investigation report and results filed by staff.1
11/15/2004Joint application for approval of assumption of certificate conditions that apply to the switchyard associated with the Fremont Energy Center filed by S. Bloomfield on behalf of Calpine Corporation and C. Schraff on behalf American Transmission Systems Incorporated.3
02/26/2004Staff has reviewed the FirstEnergys drawing T-675-04-01 titled West Fremont Property Plan for the Ohio Power Siting Boards review and approval.1
02/18/2004Drawing T-675-04-01, titled "West Fremont Property Plan" for the OPSB's review and approval, filed on behalf of FirstEnergy Service Corp. by T. Krauss.3
12/15/2003Entry ordering that the May 21, 2001, as amended on June 18, 2001 certificate of environmental compatibility and public need previously granted to Fremont Energy Center, LLC for the construction and operation of a 704-MW electric generating station in Sandusky Township, Sandusky, Ohio, shall be transferred to Calpine Corporation, ordered that Calpine Corp. shall be bound by and comply with all terms and conditions of the certificate.(OPSB)3
12/15/2003Entry ordering that the May 21, 2001, as amended on June 18, 2001 certificate of environmental compatibility and public need previously granted to Fremont Energy Center LLC for construction and operation of a 704-MW electric generating station shall be transferred to Calpine Corporation and that as a result of transfer, Calpine Corporation shall be bound by and comply with all terms and conditions of this certificate.3
11/24/2003Letter confirming merger closed on November 18, 2003, filed on behalf of Fremont Energy Center, LLC by S. Bloomfield.1
10/22/2003Notice of merger; or in the alternative, application to transfer a certificate to the surviving corporation of a merger with its parent corporation, filed on behalf of Fremont Energy Center LLC and Calpine Corporation by S. Bloomfield.4
10/11/2001Letter to Sally Bloomfield stating that the filing does meet with the informational requirements and applicant may proceed with construction of the facility, filed by K. Lambeck, PUCO staff.1
09/17/2001Correspondence to L. Winget, PUCO staff, regarding Nationwide Permit No. 12 for the City of Fremont, filed on behalf of applicant by S. Bloomfield.1
08/29/2001Letter to Sally W. Bloomfield stating that Fremont Energy Center LLC may proceed with the construction of the facility, filed by K. Lambeck, PUCO staff.1
08/28/2001Letter stating that applicant plans to commence construction on Tuesday, September 4, 2001, filed by S. Bloomfield.1
08/21/2001Letter to L. Winget, PUCO staff, regarding the wastewater pretreatment facilities permit, filed on behalf of applicant by S. Bloomfield.1
08/21/2001Letter requesting the PUCO staff to issue a letter stating that it may proceed with construction in accordance with the conditions of its certificate, filed on behalf of applicant by S. Bloomfield.2
08/15/2001The Ohio EPA Permit To Install, Sandusky County, Application No. 03-13549, effective August 9, 2001, filed on behalf of applicant by S. Bloomfield.51
08/07/2001Response filed on behalf of the Ohio Environmental Protection Agency by M. Hopkins.4
08/07/2001Additional information filed on behalf of applicant by S. Bloomfield.6
07/30/2001Drainage Study for Fremont Energy Center filed.88
07/02/2001Letter stating that today under separate cover, the Ohio EPA Storm Water General Permit Number OHR110373 was provided to the Ohio Power Siting Board, filed on behalf of applicant by S. Bloomfield.1
06/22/2001Letter confirming that today under separate cover, Fremont Energy Center LLC provided to the Ohio Power Siting Board copies of the Construction Storm Water Pollution Prevention Plan, filed by S. Bloomfield.1
06/21/2001Letter stating that today at the pre-construction meeting, Fremont Energy Center provided to the Ohio Power Siting Board staff the evaluation of the potential impacts and proposed mitigative measures to be utilized during the construction of the water and wastewater lines to the Fremont Energy Center, filed by S. Bloomfield.1
06/21/2001Letter stating that today under separate cover, Fremont Energy Center provided to the Ohio Power Siting Board the Facilities Study of June 19, 2001, filed by S. Bloomfield.1
06/19/2001Service Notice.1
06/19/2001Letter confirming that today under separate cover, Fremont Energy Center LLC provided to the Ohio Power Siting Board the Facilities Study of June 2001 prepared by AEP, filed on behalf of applicant by S. Bloomfield.1
06/18/2001Entry Nunc Pro Tunc ordering that the May 21, 2001 opinion, order, and certificate be modified, nunc pro tunc, to reflect, as a fourth condition of the certificate, the language set forth in Finding 3 of this entry. (OPSB)2
06/01/2001Additional information filed on behalf of applicant. (Oversized documents)1
06/01/2001Letter confirming that today under separate cover, applicant provided to the Ohio Power Siting Board staff site plans and engineering drawings and the Drainage Study for this project, filed by S. Bloomfield.1
05/29/2001Request that the Board issue an entry nunc pro tunc or an errata which corrects Condition No. 4 in the Opinion, Order and Certificate issued in this case, filed on behalf of applicant by S. Bloomfield.4
05/22/2001Service Notice.3
05/21/2001Opinion, order, and certificate approving stipulation; a certificate of environmental compatibility and public need be issued; certificate must contain the 25 conditions set forth in Section V.19
05/17/2001Letter confirming that today under separate cover, Fremont Energy provided to the Ohio Power Siting Board staff the FirstEnergy interconnection studies compiles into one report-the System Impact Studies-which includes the Short Circuit Analysis, dated May 2001, filed on behalf of applicant by S. Bloomfield.1
05/11/2001Update to the stipulation filed on March 29, 2001, filed on behalf of the PUCO staff by S. Nourse; and applicant by S. Bloomfield.2
05/09/2001Letter confirming that today under separate cover, applicant provided to the Ohio Power Siting Board staff the Stability Analysis which has been completed, filed on behalf of applicant by S. Bloomfield.1
05/09/2001Correspondence to Leon Winget, PUCO staff, regarding the Stability Analysis, filed on behalf of applicant by S. Bloomfield.1
05/09/2001Letter confirming that today under separate cover, Fremont Energy Center provided to the Ohio Power Siting Board staff the Stability Analysis which has been completed, filed by S. Bloomfield.1
04/17/2001Letter and brochure from the Black Swamp Bird Observatory clarifying their position on the Fremont Energy Center, filed on behalf of applicant by S. Bloomfield.4
04/11/2001Transcript for hearing held 3/28/01, submitted. (SF)(PUCO-Columbus, OH)32
04/02/2001Transcript for public hearing held 3/27/01 in Fremont, Ohio, concluded. (SF)49
03/29/2001Joint stipulation and recommendation filed on behalf of the PUCO Power Siting Board staff by S. Nourse and M. Malone; and applicant by S. Bloomfield.11
03/27/2001Letter with ad supporting new power plants in California filed by S. Bloomfield.2
03/19/2001Comments and supporting information filed by C. Frampton80
03/13/2001Service Notice.5
03/12/2001Staff Report filed.43
03/12/2001Proof of Publication filed on behalf of applicant by S. Bloomfield. (Sandusky County)3
03/09/2001Letter documenting the fact that Dr. Winget was provided with the following documents: System Impact Study, Phase I, power flow analysis dated March 2001 from FirstEnergy; System Impact Study, Phase 1, power flow analysis dated January 2001 from AEP; and System Impact Study, Phase 2, short circuit analysis dated January 2001 from AEP, filed on behalf of applicant by S. Bloomfield.1
02/13/2001Letter regarding copies of (1) Phase I Archeological Survey of Two Proposed Alternatives for the Fremont Energy Project filed by S. Bloomfield.1
02/08/2001Proof of letter mailing to area property owners and submission of property owners' mailing list, filed on behalf of applicant by S. Bloomfield.184
01/25/2001Responses to Staff's first set of interrogatories/request for documents, filed on behalf of applicant.45
01/23/2001Affidavit of publication filed by S. Bloomfield.3
01/22/2001Proof of Publication filed on behalf of applicant by S. Bloomfield. (Sandusky County)4
01/09/2001First set of interrogatories and request for production of documents to applicant, filed on behalf of the PUCO staff by J. Martin.7
01/09/2001Service Notice.7
01/08/2001Entry scheduling a hearing at 6:30 p.m. on March 27, 2001, at the Terra Community College, Fremont, Ohio; scheduling an adjudicatory hearing at 11:00 a.m. on March 28, 2001, at the Commission offices. (AE)2
01/03/2001Proof of service of certified application filed on behalf of applicant by S. Bloomfield.2
01/02/2001Proof of service of certified application on appropriate public officials and library, filed on behalf of applicant by S. Bloomfield.81
01/02/2001Copy of check made out to Treasurer, State of Ohio, Ohio Power Siting Board, filed on behalf of applicant by S. Bloomfield.2
12/22/2000Correspondence letter to Sally W. Bloomfield stating that application has been found to comply with Chapters 4906/01, et seq. of the Ohio Administrative Code, filed on behalf of the PUCO staff.2
12/15/2000Response filed on behalf of applicant by S. Bloomfield.3
12/15/2000Study conducted by Calypso Research dated October 2, 2000, filed on behalf of applicant by S. Bloomfield.28
12/13/2000Entry granting motion for waivers. (SF) (filed 12/12/00)5
12/06/2000Document showing the results of a noise study that was conducted by applicant, filed on behalf of applicant by S. Bloomfield.2
12/05/2000Letter informing the Commission that on this day applicant has provided to Mr. Winget copies of two System Impact Studies, one completed by ATSI Transmission System (FirstEnergy) and one by AEP Transmission System, filed by S. Bloomfield.1
09/29/2000Application for certificate of environmental compatibility and public need.211
08/31/2000ICN #0002 Proof of Publication filed on behalf of appli- cant by S. Bloomfield. (3 pgs.) (Sandusky County)3
08/21/2000ICN #0001 In the matter of the application of Freemont Energy Center LLC for a certificate of environmental compatability and public need for a merchant, combined- cycle, 704 MW power plant in Sandusky, Ohio. (14 pgs.)14