03/24/2015 | Memo closing case with an effective date of 3/24/15. | 1 |
02/23/2012 | Notice of compliance filed by S. Doran on behalf of American Municipal Power, Inc.. | 2 |
07/27/2011 | Service Notice | 2 |
07/25/2011 | Service Notice | 4 |
07/25/2011 | Entry ordered that the joint application to transfer the certificate from FirstEnergy to AMP be granted; that as a result of this transfer,AMP shall be bound by and comply with all terms and conditions of this certificate. | 3 |
06/24/2011 | Letter in support of joint application to transfer a certificate to American Municipal Power filed by C. Schraff on behalf of FirstEnergy Generation Corp. | 3 |
06/23/2011 | Notice of service of local government officials filed by R. Schmidt, Jr. on behalf of FirstEnergy Generation Corp. | 9 |
05/25/2011 | Amended Joint Application to Transfer a Certificate to American Municipal Power, Inc. filed by R. Schmidt, Jr. of FirstEnergy Generation Corp. and S. Doran of American Municipal Power, Inc. | 5 |
05/23/2011 | Joint Application of FirstEnergy Generation Corp and American Municipal Power, Inc. to transfer a certificate to American Municipal Power, Inc. filed by R. Schmidt, Jr. and Scott M. Doran on behalf of FirstEnergy Generation Corp and American Municipal Power, Inc. | 5 |
03/04/2008 | Service Notice | 4 |
03/03/2008 | Entry ordering that the application to transfer the certificate of environmental compatibility and public need for the construction and operation of the 704-MW electric generating station in Fremont, Sandusky County, Ohio from Calpine to FirstEnergy Generation Corp. is granted upon terms set forth in finding (5). (OPSB) | 3 |
02/15/2008 | Amended joint application to transfer a certificate to FirstEnergy Generation Corp. filed on behalf of Calpine Corporation, Inc and FirstEnergy Generation Corp. by S. Bloomfield and C. Schraff. | 2 |
02/11/2008 | Joint application of Fremont Energy Center LLC and FirstEnergy Generation Corp.to transfer certificate filed on behalf of FirstEnergy Generation Corp. by S. Bloomfield and C. Schraff. | 3 |
12/22/2006 | Report on construction activity for year 2006, filed on behalf of Fremont Energy Center by K. Florence. | 1 |
06/02/2005 | Annual progress report of Fremont Energy Center Construction filed by J. Garvey. | 2 |
01/13/2005 | Service Notice | 2 |
01/10/2005 | Entry approving the joint application of Calpine and ATSI permitting ATSI to assume the obligations of the certificate conditions related ti the Fremont Energy Center switchyard. | 3 |
11/16/2004 | Staff investigation report and results filed by staff. | 1 |
11/15/2004 | Joint application for approval of assumption of certificate conditions that apply to the switchyard associated with the Fremont Energy Center filed by S. Bloomfield on behalf of Calpine Corporation and C. Schraff on behalf American Transmission Systems Incorporated. | 3 |
02/26/2004 | Staff has reviewed the FirstEnergys drawing T-675-04-01 titled West Fremont Property Plan for the Ohio Power Siting Boards review and approval. | 1 |
02/18/2004 | Drawing T-675-04-01, titled "West Fremont Property Plan" for the OPSB's review and approval, filed on behalf of FirstEnergy Service Corp. by T. Krauss. | 3 |
12/15/2003 | Entry ordering that the May 21, 2001, as amended on June 18, 2001 certificate of environmental compatibility and public need previously granted to Fremont Energy Center, LLC for the construction and operation of a 704-MW electric generating station in Sandusky Township, Sandusky, Ohio, shall be transferred to Calpine Corporation, ordered that Calpine Corp. shall be bound by and comply with all terms and conditions of the certificate.(OPSB) | 3 |
12/15/2003 | Entry ordering that the May 21, 2001, as amended on June 18, 2001 certificate of environmental compatibility and public need previously granted to Fremont Energy Center LLC for construction and operation of a 704-MW electric generating station shall be transferred to Calpine Corporation and that as a result of transfer, Calpine Corporation shall be bound by and comply with all terms and conditions of this certificate. | 3 |
11/24/2003 | Letter confirming merger closed on November 18, 2003, filed on behalf of Fremont Energy Center, LLC by S. Bloomfield. | 1 |
10/22/2003 | Notice of merger; or in the alternative, application to transfer a certificate to the surviving corporation of a merger with its parent corporation, filed on behalf of Fremont Energy Center LLC and Calpine Corporation by S. Bloomfield. | 4 |
10/11/2001 | Letter to Sally Bloomfield stating that the filing does meet with the informational requirements and applicant may proceed with construction of the facility, filed by K. Lambeck, PUCO staff. | 1 |
09/17/2001 | Correspondence to L. Winget, PUCO staff, regarding Nationwide Permit No. 12 for the City of Fremont, filed on behalf of applicant by S. Bloomfield. | 1 |
08/29/2001 | Letter to Sally W. Bloomfield stating that Fremont Energy Center LLC may proceed with the construction of the facility, filed by K. Lambeck, PUCO staff. | 1 |
08/28/2001 | Letter stating that applicant plans to commence construction on Tuesday, September 4, 2001, filed by S. Bloomfield. | 1 |
08/21/2001 | Letter to L. Winget, PUCO staff, regarding the wastewater pretreatment facilities permit, filed on behalf of applicant by S. Bloomfield. | 1 |
08/21/2001 | Letter requesting the PUCO staff to issue a letter stating that it may proceed with construction in accordance with the conditions of its certificate, filed on behalf of applicant by S. Bloomfield. | 2 |
08/15/2001 | The Ohio EPA Permit To Install, Sandusky County, Application No. 03-13549, effective August 9, 2001, filed on behalf of applicant by S. Bloomfield. | 51 |
08/07/2001 | Response filed on behalf of the Ohio Environmental Protection Agency by M. Hopkins. | 4 |
08/07/2001 | Additional information filed on behalf of applicant by S. Bloomfield. | 6 |
07/30/2001 | Drainage Study for Fremont Energy Center filed. | 88 |
07/02/2001 | Letter stating that today under separate cover, the Ohio EPA Storm Water General Permit Number OHR110373 was provided to the Ohio Power Siting Board, filed on behalf of applicant by S. Bloomfield. | 1 |
06/22/2001 | Letter confirming that today under separate cover, Fremont Energy Center LLC provided to the Ohio Power Siting Board copies of the Construction Storm Water Pollution Prevention Plan, filed by S. Bloomfield. | 1 |
06/21/2001 | Letter stating that today at the pre-construction meeting, Fremont Energy Center provided to the Ohio Power Siting Board staff the evaluation of the potential impacts and proposed mitigative measures to be utilized during the construction of the water and wastewater lines to the Fremont Energy Center, filed by S. Bloomfield. | 1 |
06/21/2001 | Letter stating that today under separate cover, Fremont Energy Center provided to the Ohio Power Siting Board the Facilities Study of June 19, 2001, filed by S. Bloomfield. | 1 |
06/19/2001 | Service Notice. | 1 |
06/19/2001 | Letter confirming that today under separate cover, Fremont Energy Center LLC provided to the Ohio Power Siting Board the Facilities Study of June 2001 prepared by AEP, filed on behalf of applicant by S. Bloomfield. | 1 |
06/18/2001 | Entry Nunc Pro Tunc ordering that the May 21, 2001 opinion, order, and certificate be modified, nunc pro tunc, to reflect, as a fourth condition of the certificate, the language set forth in Finding 3 of this entry. (OPSB) | 2 |
06/01/2001 | Additional information filed on behalf of applicant. (Oversized documents) | 1 |
06/01/2001 | Letter confirming that today under separate cover, applicant provided to the Ohio Power Siting Board staff site plans and engineering drawings and the Drainage Study for this project, filed by S. Bloomfield. | 1 |
05/29/2001 | Request that the Board issue an entry nunc pro tunc or an errata which corrects Condition No. 4 in the Opinion, Order and Certificate issued in this case, filed on behalf of applicant by S. Bloomfield. | 4 |
05/22/2001 | Service Notice. | 3 |
05/21/2001 | Opinion, order, and certificate approving stipulation; a certificate of environmental compatibility and public need be issued; certificate must contain the 25 conditions set forth in Section V. | 19 |
05/17/2001 | Letter confirming that today under separate cover, Fremont Energy provided to the Ohio Power Siting Board staff the FirstEnergy interconnection studies compiles into one report-the System Impact Studies-which includes the Short Circuit Analysis, dated May 2001, filed on behalf of applicant by S. Bloomfield. | 1 |
05/11/2001 | Update to the stipulation filed on March 29, 2001, filed on behalf of the PUCO staff by S. Nourse; and applicant by S. Bloomfield. | 2 |
05/09/2001 | Letter confirming that today under separate cover, applicant provided to the Ohio Power Siting Board staff the Stability Analysis which has been completed, filed on behalf of applicant by S. Bloomfield. | 1 |
05/09/2001 | Correspondence to Leon Winget, PUCO staff, regarding the Stability Analysis, filed on behalf of applicant by S. Bloomfield. | 1 |
05/09/2001 | Letter confirming that today under separate cover, Fremont Energy Center provided to the Ohio Power Siting Board staff the Stability Analysis which has been completed, filed by S. Bloomfield. | 1 |
04/17/2001 | Letter and brochure from the Black Swamp Bird Observatory clarifying their position on the Fremont Energy Center, filed on behalf of applicant by S. Bloomfield. | 4 |
04/11/2001 | Transcript for hearing held 3/28/01, submitted. (SF)(PUCO-Columbus, OH) | 32 |
04/02/2001 | Transcript for public hearing held 3/27/01 in Fremont, Ohio, concluded. (SF) | 49 |
03/29/2001 | Joint stipulation and recommendation filed on behalf of the PUCO Power Siting Board staff by S. Nourse and M. Malone; and applicant by S. Bloomfield. | 11 |
03/27/2001 | Letter with ad supporting new power plants in California filed by S. Bloomfield. | 2 |
03/19/2001 | Comments and supporting information filed by C. Frampton | 80 |
03/13/2001 | Service Notice. | 5 |
03/12/2001 | Staff Report filed. | 43 |
03/12/2001 | Proof of Publication filed on behalf of applicant by S. Bloomfield. (Sandusky County) | 3 |
03/09/2001 | Letter documenting the fact that Dr. Winget was provided with the following documents: System Impact Study, Phase I, power flow analysis dated March 2001 from FirstEnergy; System Impact Study, Phase 1, power flow analysis dated January 2001 from AEP; and System Impact Study, Phase 2, short circuit analysis dated January 2001 from AEP, filed on behalf of applicant by S. Bloomfield. | 1 |
02/13/2001 | Letter regarding copies of (1) Phase I Archeological Survey of Two Proposed Alternatives for the Fremont Energy Project filed by S. Bloomfield. | 1 |
02/08/2001 | Proof of letter mailing to area property owners and submission of property owners' mailing list, filed on behalf of applicant by S. Bloomfield. | 184 |
01/25/2001 | Responses to Staff's first set of interrogatories/request for documents, filed on behalf of applicant. | 45 |
01/23/2001 | Affidavit of publication filed by S. Bloomfield. | 3 |
01/22/2001 | Proof of Publication filed on behalf of applicant by S. Bloomfield. (Sandusky County) | 4 |
01/09/2001 | First set of interrogatories and request for production of documents to applicant, filed on behalf of the PUCO staff by J. Martin. | 7 |
01/09/2001 | Service Notice. | 7 |
01/08/2001 | Entry scheduling a hearing at 6:30 p.m. on March 27, 2001, at the Terra Community College, Fremont, Ohio; scheduling an adjudicatory hearing at 11:00 a.m. on March 28, 2001, at the Commission offices. (AE) | 2 |
01/03/2001 | Proof of service of certified application filed on behalf of applicant by S. Bloomfield. | 2 |
01/02/2001 | Proof of service of certified application on appropriate public officials and library, filed on behalf of applicant by S. Bloomfield. | 81 |
01/02/2001 | Copy of check made out to Treasurer, State of Ohio, Ohio Power Siting Board, filed on behalf of applicant by S. Bloomfield. | 2 |
12/22/2000 | Correspondence letter to Sally W. Bloomfield stating that application has been found to comply with Chapters 4906/01, et seq. of the Ohio Administrative Code, filed on behalf of the PUCO staff. | 2 |
12/15/2000 | Response filed on behalf of applicant by S. Bloomfield. | 3 |
12/15/2000 | Study conducted by Calypso Research dated October 2, 2000, filed on behalf of applicant by S. Bloomfield. | 28 |
12/13/2000 | Entry granting motion for waivers. (SF) (filed 12/12/00) | 5 |
12/06/2000 | Document showing the results of a noise study that was conducted by applicant, filed on behalf of applicant by S. Bloomfield. | 2 |
12/05/2000 | Letter informing the Commission that on this day applicant has provided to Mr. Winget copies of two System Impact Studies, one completed by ATSI Transmission System (FirstEnergy) and one by AEP Transmission System, filed by S. Bloomfield. | 1 |
09/29/2000 | Application for certificate of environmental compatibility and public need. | 211 |
08/31/2000 | ICN #0002 Proof of Publication filed on behalf of appli- cant by S. Bloomfield. (3 pgs.) (Sandusky County) | 3 |
08/21/2000 | ICN #0001 In the matter of the application of Freemont Energy Center LLC for a certificate of environmental compatability and public need for a merchant, combined- cycle, 704 MW power plant in Sandusky, Ohio. (14 pgs.) | 14 |