DIS - Case Record for 99-0580-RR-STP Skip to main content

Case Record For:

99-0580-RR-STP

File a Public Comment
Case Title: CONRAIL/WAYNE COUNTY COMMISSIONERS
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: STP-State funded warning projects
Date Opened: 5/11/1999
Date Closed: 11/20/2001
Printable Docket Card Service List
View All
1 - 15 of 18 documents 1 /  2 
Date FiledSummaryPages
11/20/2001Service Notice2
11/20/2001Service Notice2
11/20/2001Entry closing this case of record.1
11/13/2001Recommended that the legal staff proceed with an entry to close the cases.4
07/25/2000Final reports of inspector Robert J. Reustle, filed on behalf of the PUCO staff by B. Johrendt. (4 pgs.)4
05/04/2000Entry ordering that the completion date for these projects be extended until June 30, 2000. (2 pgs.)2
05/04/2000Entry ordering that the completion date for these projects be extended until June 30, 2000.3
03/15/2000Memo filed by B. Johrendt, PUCO staff, (with attached letter from Norfolk Southern) stating that the new deadline for completion is June 19, 2000. (3 pgs.)3
03/15/2000Memo filed by B. Johrendt, PUCO staff, (with attached letter from Norfolk Southern) stating that the new deadline for completion is June 19, 2000.3
03/14/2000Request for an extension of time in which to complete the grade crossing warning device installation projects at TWP 68/Geyers Road (502-496X), CR 73/Eby Road (502-498L) and CR 23/Back Orrville road (503-057S) in Wayne County, filed on behalf of Norfolk Southern Railway by R. Noe.2
03/14/2000Request for an extension of time in which to complete the grade crossing warning device installation projects at TWP 68/Geyers Road (502-496X), CR 73/Eby Road (502-498L) and CR 23/Back Orrville road (503-057S) in Wayne County, filed on behalf of Norfolk Southern Railway by R. Noe. (2 pgs.)2
03/03/2000Entry ordering that the site plans and cost estimates for listed projects be apparoved; that the funding for the involved parties be reallocated as set forth in Finding 3; that NS complete construction and installation by May 19, 2000.3
02/03/2000Entry ordering that the site plans and cost estimates for listed projects be apparoved; that the funding for the involved parties be reallocated as set forth in Finding 3; that NS complete construction and installation by May 19, 2000. (3 pgs.)3
01/27/2000Memo, field and office report, and construction authori- zation filed by B. Johrendt, PUCO staff. (4 pgs.)4
01/27/2000Memo, field and office report, and construction authori- zation filed by B. Johrendt, PUCO staff.4
 
1 /  2 
      
      
Attorney General:
Attorney Examiner:
Farkas, Scott