11/20/2001
|
Service Notice |
11/20/2001
|
Service Notice |
11/20/2001
|
Entry closing this case of record. |
11/13/2001
|
Recommended that the legal staff proceed with an entry to close the cases. |
07/25/2000
|
Final reports of inspector Robert J. Reustle, filed on behalf of the PUCO staff by B. Johrendt. (4 pgs.) |
05/04/2000
|
Entry ordering that the completion date for these projects be extended until June 30, 2000. (2 pgs.) |
05/04/2000
|
Entry ordering that the completion date for these projects be extended until June 30, 2000. |
03/15/2000
|
Memo filed by B. Johrendt, PUCO staff, (with attached letter from Norfolk Southern) stating that the new deadline for completion is June 19, 2000. (3 pgs.) |
03/15/2000
|
Memo filed by B. Johrendt, PUCO staff, (with attached letter from Norfolk Southern) stating that the new deadline for completion is June 19, 2000. |
03/14/2000
|
Request for an extension of time in which to complete the grade crossing warning device installation projects at TWP 68/Geyers Road (502-496X), CR 73/Eby Road (502-498L) and CR 23/Back Orrville road (503-057S) in Wayne County, filed on behalf of Norfolk Southern Railway by R. Noe. |
03/14/2000
|
Request for an extension of time in which to complete the grade crossing warning device installation projects at TWP 68/Geyers Road (502-496X), CR 73/Eby Road (502-498L) and CR 23/Back Orrville road (503-057S) in Wayne County, filed on behalf of Norfolk Southern Railway by R. Noe. (2 pgs.) |
03/03/2000
|
Entry ordering that the site plans and cost estimates for listed projects be apparoved; that the funding for the involved parties be reallocated as set forth in Finding 3; that NS complete construction and installation by May 19, 2000. |
02/03/2000
|
Entry ordering that the site plans and cost estimates for listed projects be apparoved; that the funding for the involved parties be reallocated as set forth in Finding 3; that NS complete construction and installation by May 19, 2000. (3 pgs.) |
01/27/2000
|
Memo, field and office report, and construction authori- zation filed by B. Johrendt, PUCO staff. (4 pgs.) |
01/27/2000
|
Memo, field and office report, and construction authori- zation filed by B. Johrendt, PUCO staff. |
05/19/1999
|
Entry adopting the stipulation; that Conrail submit to the Commission site plans and cost estimates for the projects within 90 days of the date of this entry; that Conrail pro- ceed with construction of the projects, with construction to be completed by May 19, 2000. (3 pgs.) |
05/19/1999
|
Service Notice |
05/11/1999
|
In the matter of a request for the installation of roadway gates and flashing lights at the Conrail grade crossings of Twp 68/Geyers Rd. (502-496X), CR 73/Eby Rd. (502-498L), and CR 23/Back Orrville Rd. (503-057S), Wayne County. (13 pgs.) |