Date Filed | Summary | Pages |
11/20/2001 | Service Notice | 2 |
11/20/2001 | Service Notice | 2 |
11/20/2001 | Entry closing this case of record. | 1 |
11/13/2001 | Recommended that the legal staff proceed with an entry to close the cases. | 4 |
07/25/2000 | Final reports of inspector Robert J. Reustle, filed on behalf of the PUCO staff by B. Johrendt. (4 pgs.) | 4 |
05/04/2000 | Entry ordering that the completion date for these projects be extended until June 30, 2000. (2 pgs.) | 2 |
05/04/2000 | Entry ordering that the completion date for these projects be extended until June 30, 2000. | 3 |
03/15/2000 | Memo filed by B. Johrendt, PUCO staff, (with attached letter from Norfolk Southern) stating that the new deadline for completion is June 19, 2000. (3 pgs.) | 3 |
03/15/2000 | Memo filed by B. Johrendt, PUCO staff, (with attached letter from Norfolk Southern) stating that the new deadline for completion is June 19, 2000. | 3 |
03/14/2000 | Request for an extension of time in which to complete the grade crossing warning device installation projects at TWP 68/Geyers Road (502-496X), CR 73/Eby Road (502-498L) and CR 23/Back Orrville road (503-057S) in Wayne County, filed on behalf of Norfolk Southern Railway by R. Noe. | 2 |
03/14/2000 | Request for an extension of time in which to complete the grade crossing warning device installation projects at TWP 68/Geyers Road (502-496X), CR 73/Eby Road (502-498L) and CR 23/Back Orrville road (503-057S) in Wayne County, filed on behalf of Norfolk Southern Railway by R. Noe. (2 pgs.) | 2 |
03/03/2000 | Entry ordering that the site plans and cost estimates for listed projects be apparoved; that the funding for the involved parties be reallocated as set forth in Finding 3; that NS complete construction and installation by May 19, 2000. | 3 |
02/03/2000 | Entry ordering that the site plans and cost estimates for listed projects be apparoved; that the funding for the involved parties be reallocated as set forth in Finding 3; that NS complete construction and installation by May 19, 2000. (3 pgs.) | 3 |
01/27/2000 | Memo, field and office report, and construction authori- zation filed by B. Johrendt, PUCO staff. (4 pgs.) | 4 |
01/27/2000 | Memo, field and office report, and construction authori- zation filed by B. Johrendt, PUCO staff. | 4 |