Date Filed | Summary | Pages |
02/12/1999 | Notification that the construction notice meets the informational requirements and the waiver of the 60 day filing time period in granted. Filed by PUCO staff. (1 pg) | 1 |
02/09/1999 | ICN #0002 Motion for waiver of contruction notice require- ments of Rule 4906-5-03(B)(1) O.A.C. filed on behalf of applicant by M. Beiting. (12 pgs.) | 12 |
02/09/1999 | ICN #0001 In the matter of the application of Toledo Edison Company to relocate a 0.15 mile section of the single cir- cuit wood pole Bryan-Edgerton 69 kV transmission line by construction of a 0.16 mile wood pole single transmission line section. (1 pg.) | 1 |