Date Filed | Summary | Pages |
10/11/2001 | Entry closing cases this case of record. | 2 |
09/27/2001 | Memorandum recommending that the legal staff proceed with an entry to close this case of record, filed by L. Dalton, PUCO staff. | 1 |
01/06/2000 | Entry ordering that NS Commence construction as a cantilever only, to be completed by January 7, 2001. | 3 |
12/16/1999 | Letter relative to the construction of cantilever crossing protection at Monroe Street, given approval by City of Bellevue, G. Haynes. | 1 |
12/03/1999 | Letter to J. Reinhardt, PUCO Staff, approving the construction of cantilever crossing protection at Monroe Street, filed on behalf of the City of Bellevue by K. Shaffer. | 3 |
01/22/1999 | Entry granting extension of time to 2/19/99 to complete installation of the three projects identified in Finding (1) (SF) (2 pgs) | 2 |
01/19/1999 | Memo from J. Reinhardt, PUCO staff, stating that staff recommends that W&LE be granted an additional 30 days within which to complete the State Route 57 project. (2 pgs.) | 2 |
01/13/1999 | Letter requesting an extension till January 31, 1999, filed by D. Reinsel. (1 pg) | 1 |
01/13/1999 | Letter requesting an extension till Feburary 15, 1999, filed by D. Reinsel. (1 pg) | 1 |
01/13/1999 | Letter requesting a deadline extension to March 18, 1999, filed by D. Reinsel. (1 pg) | 1 |
12/23/1998 | Entry ordering that the request for extensions of time to complete the installation of the projects identified in Finding 1 is granted. (AE) (2 pgs.) (ISSUED 12/22/98 INCORRECTLY IN CASE NO. 98-637-GA-AEC) | 2 |
12/17/1998 | Memo, with attached letter dated December 15, 1998, from Dan Reinsel requesting a 30 day extension of the three projects, filed by J. Reinhardt, PUCO staff. (8 pgs.) | 8 |
09/24/1998 | Entry ordering that N&W's request for an extension of time to October 18, 1998 to complete this project is granted. (SF) | 3 |
09/23/1998 | Request for extension of time until October 18, 1998 to complete the improvement because of required engineering changes in the field, filed by Walter Dissen. | 2 |
09/23/1998 | Request of Norfolk and Western Railway for a 30 day extension on project. | 1 |