10/08/1993 | Memo closing case with effective date of 10/8/93. | 0 |
11/07/1991 | ICN #0005 Letter stating that construction on this project has been completed and line was energized on September 26, 1991, filed on behalf of applicant by J. Liebrecht, Sr. | 0 |
09/19/1991 | ICN #0004 Letter stating that construction on this project is expected to begin on July 17, 1991, filed on behalf of applicant by J. Liebrecht P.E. | 0 |
07/03/1991 | ICN #0003 Investigation Report Letter of Notification filed on behalf of the OPSB staff. | 0 |
07/03/1991 | ICN #0002 Letter to J. E. Schrader in response to Letter of Notification filed on behalf of the OPSB staff by J. Kennedy. | 0 |
06/20/1991 | ICN #0001 Letter of Notification for the West Bellaire- Tiltonsville 138 Kv Line relocation, filed by Ohio Power Company. | 0 |