10/08/1993 Memo closing case with effective date of 10/8/93.
11/07/1991 ICN #0005 Letter stating that construction on this project has been completed and line was energized on September 26, 1991, filed on behalf of applicant by J. Liebrecht, Sr.
09/19/1991 ICN #0004 Letter stating that construction on this project is expected to begin on July 17, 1991, filed on behalf of applicant by J. Liebrecht P.E.
07/03/1991 ICN #0003 Investigation Report Letter of Notification filed on behalf of the OPSB staff.
07/03/1991 ICN #0002 Letter to J. E. Schrader in response to Letter of Notification filed on behalf of the OPSB staff by J. Kennedy.
06/20/1991 ICN #0001 Letter of Notification for the West Bellaire- Tiltonsville 138 Kv Line relocation, filed by Ohio Power Company.