Date Filed | Summary | Pages |
10/08/1993 | Memo closing case with effective date of 10/8/93. | 0 |
03/12/1991 | ICN #0004 Letter stating that the planned date of initial construction on this project is the week of March 4, 1991, filed on behalf of applicant by J. Ams, Sr. | 0 |
02/28/1991 | ICN #0003 Investigation report for Letter of Notification filed on behalf of OPSB staff. | 0 |
02/28/1991 | ICN #0002 Letter to Craig I. Smith, senior corporate counsel Centerior Energy, in response to Letter of Notification filed February 11, 1991, filed on behalf of the OPSB by J. Kennedy. | 0 |
02/11/1991 | ICN #0001 Letter of notification covering the installation of a single circuit l38kV supply line to the Manville Customer Distribution Substation, filed by The Toledo Edison Company. | 0 |
|