10/08/1993
|
Memo closing case with effective date of 10/8/93. |
03/12/1991
|
ICN #0004 Letter stating that the planned date of initial construction on this project is the week of March 4, 1991, filed on behalf of applicant by J. Ams, Sr. |
02/28/1991
|
ICN #0003 Investigation report for Letter of Notification filed on behalf of OPSB staff. |
02/28/1991
|
ICN #0002 Letter to Craig I. Smith, senior corporate counsel Centerior Energy, in response to Letter of Notification filed February 11, 1991, filed on behalf of the OPSB by J. Kennedy. |
02/11/1991
|
ICN #0001 Letter of notification covering the installation of a single circuit l38kV supply line to the Manville Customer Distribution Substation, filed by The Toledo Edison Company. |
|