Date Filed | Summary | Pages |
10/08/2024 | Correspondence Letter regarding Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 4 |
08/07/2024 | Notice of Proof of Compliance with the Condition 2, 3 & 6 for the Cyprus 345 kV Extension Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 57 |
07/31/2024 | Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
06/05/2024 | Service Notice. | 1 |
06/05/2024 | Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. | 7 |
03/21/2024 | Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 23 |
03/14/2024 | Letter of Notification Cyprus 345 kV Extension Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 83 |
03/08/2024 | In the Matter of the Application Pre-application Letter electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |