10/08/2024
|
Correspondence Letter regarding Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
08/07/2024
|
Notice of Proof of Compliance with the Condition 2, 3 & 6 for the Cyprus 345 kV Extension Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
07/31/2024
|
Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
06/05/2024
|
Service Notice. |
06/05/2024
|
Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. |
03/21/2024
|
Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
03/14/2024
|
Letter of Notification Cyprus 345 kV Extension Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
03/08/2024
|
In the Matter of the Application Pre-application Letter electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |