06/06/2024 | Correspondence Letter regarding Proof of Compliance w/Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 66 |
01/08/2024 | Notice of Construction Start Date electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
01/08/2024 | Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 175 |
05/12/2023 | Service Notice- Staff Report. | 3 |
05/12/2023 | Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. | 6 |
04/06/2023 | Response to Staff's 3rd Set electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 90 |
04/04/2023 | Response to Ohio Power Siting Board Staff's 2nd Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
03/06/2023 | Motion to Intervene and Memorandum in Support of Buckeye Power, Inc. electronically filed by Ms. Lija Kaleps-Clark on behalf of Buckeye Power, Inc. | 7 |
03/03/2023 | Responses to Staff's First Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 5 |
02/24/2023 | Proof of Compliance with Notice Requirements electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
02/16/2023 | Letter of Notification Application for the Fiddlestix Switch-IIesboro South Central Power 138-kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 551 |
02/13/2023 | In the Matter of the Pre-Application Notification Letter for the Fiddlestix Switch-Ilesboro South Central Power 138kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 3 |