06/06/2024
|
Correspondence Letter regarding Proof of Compliance w/Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
01/08/2024
|
Notice of Construction Start Date electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
01/08/2024
|
Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
05/12/2023
|
Service Notice- Staff Report. |
05/12/2023
|
Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. |
04/06/2023
|
Response to Staff's 3rd Set electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
04/04/2023
|
Response to Ohio Power Siting Board Staff's 2nd Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
03/06/2023
|
Motion to Intervene and Memorandum in Support of Buckeye Power, Inc. electronically filed by Ms. Lija Kaleps-Clark on behalf of Buckeye Power, Inc. |
03/03/2023
|
Responses to Staff's First Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
02/24/2023
|
Proof of Compliance with Notice Requirements electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
02/16/2023
|
Letter of Notification Application for the Fiddlestix Switch-IIesboro South Central Power 138-kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
02/13/2023
|
In the Matter of the Pre-Application Notification Letter for the Fiddlestix Switch-Ilesboro South Central Power 138kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |