08/22/2022 | Proof of Compliance, condition #4: Mill Creek electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 13 |
08/16/2022 | Notice of Start of Construction, Mill Creek-Riverview 138 kV Transmission Line Rebuild Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
03/11/2022 | Notice and Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 181 |
07/20/2021 | Service Notice | 3 |
07/20/2021 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
06/24/2021 | Notice of Adjustments electronically filed by Ms. Christen M. Blend on behalf of Ohio Power Company. | 3 |
05/11/2021 | Notice of Proof of Compliance and Associated Exhibits for the Mill Creek-Riverview 138 kV Transmission Line Rebuild electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 49 |
04/27/2021 | Letter of Notification Application for the Mill Creek-Riverview 138 kV Transmission Line (Str. 24-Str. 27) Rebuild Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 87 |
04/26/2021 | In the Matter of the Pre-Application Notification Letter for the Mill Creek-Riverview 138 kV Transmission Line Rebuild electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 3 |