DIS - Case Record for 21-0267-EL-BLN Skip to main content
      
      
CASE NUMBER: 21-0267-EL-BLN
CASE DESCRIPTION: Mill Creek-Riverview 138 kV Transmission Line Rebuild
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
08/22/2022 Proof of Compliance, condition #4: Mill Creek electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.
08/16/2022 Notice of Start of Construction, Mill Creek-Riverview 138 kV Transmission Line Rebuild Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.
03/11/2022 Notice and Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.
07/20/2021 Service Notice
07/20/2021 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
06/24/2021 Notice of Adjustments electronically filed by Ms. Christen M. Blend on behalf of Ohio Power Company.
05/11/2021 Public Comment of Michael Becker, via website, electronically filed by Docketing Staff.
05/11/2021 Notice of Proof of Compliance and Associated Exhibits for the Mill Creek-Riverview 138 kV Transmission Line Rebuild electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
04/27/2021 Letter of Notification Application for the Mill Creek-Riverview 138 kV Transmission Line (Str. 24-Str. 27) Rebuild Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
04/26/2021 In the Matter of the Pre-Application Notification Letter for the Mill Creek-Riverview 138 kV Transmission Line Rebuild electronically filed by Tanner Wolffram on behalf of Ohio Power Company.