Proof of Compliance, condition #4: Mill Creek electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
08/16/2022
|
Notice of Start of Construction, Mill Creek-Riverview 138 kV Transmission Line Rebuild Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
03/11/2022
|
Notice and Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
07/20/2021
|
Service Notice |
07/20/2021
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
06/24/2021
|
Notice of Adjustments electronically filed by Ms. Christen M. Blend on behalf of Ohio Power Company. |
05/11/2021
|
Public Comment of Michael Becker, via website, electronically filed by Docketing Staff. |
05/11/2021
|
Notice of Proof of Compliance and Associated Exhibits for the Mill Creek-Riverview 138 kV Transmission Line Rebuild electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
04/27/2021
|
Letter of Notification Application for the Mill Creek-Riverview 138 kV Transmission Line (Str. 24-Str. 27) Rebuild Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
04/26/2021
|
In the Matter of the Pre-Application Notification Letter for the Mill Creek-Riverview 138 kV Transmission Line Rebuild electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |