DIS - Case Record for 17-2190-EL-BNR Skip to main content

Case Record For:

17-2190-EL-BNR

Case Title: Galion-Longview 138kV Transmission Line Structure Addition Project
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 10/24/2017
Date Closed: 8/7/2019
Printable Docket Card Service List
View All
1 - 7 of 7 documents 1 /  1 
Date FiledSummaryPages
08/21/2019Case Action Form to Close Case electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.2
02/28/2018Notice that Project was Completed on Februray 23, 2018 filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. 1
01/08/2018Notice that the construction of Galion-Longview 138 kV Transmission Line Structure Addition Project will commence of January 10, 2018 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. 1
11/22/2017Service Notice2
11/22/2017Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.4
11/09/2017Construction Notice for Galion-Longview 138kV transmission line structure addition project filed by N. Bryksenkova on behalf of FirstEnergyServvice Company. 34
10/24/2017In the matter of the filing of the Pre-Application Notification Letter for the Gallion-Longview 138 kV Transmission Line Structure Addition Project, electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.2
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: