08/21/2019
|
Case Action Form to Close Case electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. |
02/28/2018
|
Notice that Project was Completed on Februray 23, 2018 filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. |
01/08/2018
|
Notice that the construction of Galion-Longview 138 kV Transmission Line Structure Addition Project will commence of January 10, 2018 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
|
11/22/2017
|
Service Notice |
11/22/2017
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
11/09/2017
|
Construction Notice for Galion-Longview 138kV transmission line structure addition project filed by N. Bryksenkova on behalf of FirstEnergyServvice Company. |
10/24/2017
|
In the matter of the filing of the Pre-Application Notification Letter for the Gallion-Longview 138 kV Transmission Line Structure Addition Project, electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |