08/21/2019 | Case Action Form to Close Case electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. | 2 |
02/28/2018 | Notice that Project was Completed on Februray 23, 2018 filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
01/08/2018 | Notice that the construction of Galion-Longview 138 kV Transmission Line Structure Addition Project will commence of January 10, 2018 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
| 1 |
11/22/2017 | Service Notice | 2 |
11/22/2017 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
11/09/2017 | Construction Notice for Galion-Longview 138kV transmission line structure addition project filed by N. Bryksenkova on behalf of FirstEnergyServvice Company. | 34 |
10/24/2017 | In the matter of the filing of the Pre-Application Notification Letter for the Gallion-Longview 138 kV Transmission Line Structure Addition Project, electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 2 |