Case Title: AMENDMENT ONE TO THE HAYES-WEST FREMONT 138 kV TRANSMISSION LINE PROJECT
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BTA-Application to Amend a Certificate/ Gas or Electri
Date Opened: 7/22/2016
Date Closed:
Printable Docket Card Service List
View All
1 - 11 of 11 documents 1 /  1 
Date FiledSummaryPages
10/31/2019Notice of the Completion of Construction of Project was May 29, 2019 electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.2
04/20/2017Notice of Commencement of Construction electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.3
03/02/2017Order on certificate that 16-1593-EL-BTA,16-1594-EL-BTA and 16-1595-EL-BTA be consolidated, and granting the applications filed by ATSI to amend the certificate of environmental compatibility and public need issued in the Hayes-West Fremont Case for the Hayes-West Fremont 138kV transmission line project and subject to the conditions set forth in the Hayes-West Fremont Case.7
03/02/2017Service Notice2
02/27/2017Notice of Hand Delivery of Staff Report of Investigation to Sandusky Public Library electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.2
02/23/2017Return mail. (unable to forward)1
10/27/2016Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.4
10/27/2016Service Notice1
08/12/2016Proof of Pub of the Public Notice of the Filing of Three Amendment Applications to the Hayes West Fremont 138kV Transmission Line Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc..14
07/29/2016Letter of Notification for Amendments to the Hayes-West Fremont 138kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company.82
07/22/2016In the Matter of the Pre-Application Notification Letter, Amendment One to the Hayes-West Fremont 138 kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company.1
 