Date Filed | Summary | Pages |
10/31/2019 | Notice of the Completion of Construction of Project was May 29, 2019 electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |
04/20/2017 | Notice of Commencement of Construction electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 3 |
03/02/2017 | Order on certificate that 16-1593-EL-BTA,16-1594-EL-BTA and 16-1595-EL-BTA be consolidated, and granting the applications filed by ATSI to amend the certificate of environmental compatibility and public need issued in the Hayes-West Fremont Case for the Hayes-West Fremont 138kV transmission line project and subject to the conditions set forth in the Hayes-West Fremont Case. | 7 |
03/02/2017 | Service Notice | 2 |
02/27/2017 | Notice of Hand Delivery of Staff Report of Investigation to Sandusky Public Library electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |
02/23/2017 | Return mail. (unable to forward) | 1 |
10/27/2016 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
10/27/2016 | Service Notice | 1 |
08/12/2016 | Proof of Pub of the Public Notice of the Filing of Three Amendment Applications to the Hayes West Fremont 138kV Transmission Line Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.. | 14 |
07/29/2016 | Letter of Notification for Amendments to the Hayes-West Fremont 138kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company. | 82 |
07/22/2016 | In the Matter of the Pre-Application Notification Letter, Amendment One to the Hayes-West Fremont 138 kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company. | 1 |