Case Title: Philo-Canton 138kV Transmission Line Relocation Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 6/30/2016
Date Closed:
Printable Docket Card Service List
View All
1 - 7 of 7 documents 1 /  1 
Date FiledSummaryPages
05/07/2018Notification that project was completed on December 1, 2017 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.2
02/09/2017Notification of Start of Construction for the Philo-Canton 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company.2
07/26/2016Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB.3
07/15/2016Correspondence - Public Notification Compliance Filing electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.2
07/15/2016Correspondence - Officials Notification Compliance Filing electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.2
07/11/2016Correspondence -Construction Notice electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company.47
06/30/2016In the matter of the letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.2
 