05/07/2018
|
Notification that project was completed on December 1, 2017 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
02/09/2017
|
Notification of Start of Construction for the Philo-Canton 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
07/26/2016
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. |
07/15/2016
|
Correspondence - Public Notification Compliance Filing electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
07/15/2016
|
Correspondence - Officials Notification Compliance Filing electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
07/11/2016
|
Correspondence -Construction Notice electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
06/30/2016
|
In the matter of the letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |