Case Title: Current Power & Gas Inc.
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: CRS-Certification application for the retail
Date Opened: 2/26/2016
Date Closed:
Printable Docket Card Service List
View All
1 - 15 of 48 documents 1 /  4 
Date FiledSummaryPages
05/16/2024Correspondence Regarding the Status of Customers that have not been Transitioned to the EDUs' SSO electronically filed by Teresa Orahood on behalf of Devin Parram on behalf of the Chief Transition Officer of Current Energy and Renewables, Inc.2
05/15/2024Service Notice.3
05/15/2024Entry affirming the directives set forth in the May 8, 2024 Entry, including the termination of the supplier coordination agreements between the Ohio Power Company d/b/a AEP Ohio and Duke Energy Ohio, Inc. and Current Energy and Renewables, Inc. Additionally, the Commission grants the request to terminate the supplier coordination agreements between Current Energy and Renewables, Inc. and The Dayton Power and Light Company d/b/a AES Ohio, and Ohio Edison Company, The Cleveland Electric Illuminating Company, and The Toledo Edison Company electronically filed by Ms. Mary E. Fischer on behalf of Public Utilities Commission of Ohio.7
05/13/2024Notice of Default and Request to Terminate Alternate Generation Supplier Coordination Agreement and Related Agreements electronically filed by Mr. Christopher C. Hollon on behalf of The Dayton Power and Light Company d/b/a AES Ohio.9
05/09/2024Notification of Default electronically filed by Ms. Kari D. Hehmeyer on behalf of The Toledo Edison Company and The Cleveland Electric Illuminating Company and Ohio Edison Company.5
05/08/2024Service Notice.3
05/08/2024Administrative Law Judge Entry ordering that AEP Ohio and Duke’s requests for termination of the coordination agreements with Current be approved; that the AEP Ohio and Duke immediately begin the process of transitioning Current’s customers back to the SSO load; that Current advise the Commission’s Service Monitoring and Enforcement Department by May 17, 2024, as to the status of all its customers not transitioned to the applicable EDU’s SSO or an alternative supplier; and that the AEP and Duke waive any applicable switching fees for those Current customers who choose an alternative supplier in the next 60 days electronically filed by Ms. Donielle M. Hunter on behalf of Jason W. Tonn, Administrative Law Judge, Public Utilities Commission of Ohio.6
05/02/2024Correspondence regarding the Notification of Default and Request for Authorization to Terminate or Suspend Participation filed on May 1, 2024 electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco and Akhbari, Elyse.4
05/01/2024Correspondence Regarding Notice Received April 2024 from Current Energy Renewables, Inc. electronically filed by Mr. Michael J. Schuler on behalf of Ohio Power Company.4
05/01/2024Notification of Default and Request for Authorization to Terminate or Suspend Participation electronically filed by Ms. Emily Olive on behalf of Duke Energy Ohio and D'Ascenzo, Rocco O. Mr. and Kingery, Jeanne W. Ms. and Vaysman, Larisa M. Ms. and Akhbari, Elyse H. Ms.4
04/30/2024Notice of Insolvency and Default of Current Energy and Renewables, Inc. electronically filed by Teresa Orahood on behalf of Devin D. Parram.24
04/30/2024Notice of Material Change electronically filed by Teresa Orahood on behalf of Devin D. Parram.14
10/24/2022Certificate No. 16-1060E issued.2
10/19/2022Confidential Document Target: Exhibit C-9. ( 2 pages ) 2
10/18/2022Confidential Document Target: Exhibit C-9. (13 pages)2
 
1 /  4 
      
      
Attorney General:
Attorney Examiner:
Tonn, Jason