Date Filed | Summary | Pages |
06/05/2015 | Construction notice stating that the Avon-Crestwood Q-3 kV Transmission Line Reconductor Project was completed on May 30, 2015 filed by W. Beutler on behalf of FirstEnergy Service Company. | 1 |
04/17/2015 | Notice informing the Commission that construction on this
project will begin on April 20, 2015 filed by W.R. Beutler, Engineer on behalf of FirstEnergy Service Company. | 1 |
02/25/2015 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 3 |
02/11/2015 | In the Matter of the Construction Notice of American Transmission Systems, Incorporated for Avon-Crestwood Q-3 138 kV Transmission Line Reconductor Project. | 10 |