CASE NUMBER: 15-0283-EL-BNR
CASE DESCRIPTION: Avon-Crestwood Q-3 138 kV Reconductor Project
DOCUMENT SIGNED ON: 5/2/2024
DATE OF SERVICE: ________________________________________
06/05/2015 Construction notice stating that the Avon-Crestwood Q-3 kV Transmission Line Reconductor Project was completed on May 30, 2015 filed by W. Beutler on behalf of FirstEnergy Service Company.
04/17/2015 Notice informing the Commission that construction on this project will begin on April 20, 2015 filed by W.R. Beutler, Engineer on behalf of FirstEnergy Service Company.
02/25/2015 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
02/11/2015 In the Matter of the Construction Notice of American Transmission Systems, Incorporated for Avon-Crestwood Q-3 138 kV Transmission Line Reconductor Project.