06/05/2015
|
Construction notice stating that the Avon-Crestwood Q-3 kV Transmission Line Reconductor Project was completed on May 30, 2015 filed by W. Beutler on behalf of FirstEnergy Service Company. |
04/17/2015
|
Notice informing the Commission that construction on this
project will begin on April 20, 2015 filed by W.R. Beutler, Engineer on behalf of FirstEnergy Service Company. |
02/25/2015
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
02/11/2015
|
In the Matter of the Construction Notice of American Transmission Systems, Incorporated for Avon-Crestwood Q-3 138 kV Transmission Line Reconductor Project. |