Date Filed | Summary | Pages |
07/17/2015 | Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 3 |
06/04/2015 | Construction Notice stating that the West Bellaire-Brues 138 kV Line was completed on October 24, 2014 electronically filed by Mr. Ajay K. Kumar on behalf of AEP Ohio Transmission Company. | 2 |
06/03/2013 | Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 3 |
04/29/2013 | In the matter of the letter of Notification -Construction Notification West Bellaire-Brues 138 kV (Stringing Second Line) electronically filed by Erin C Miller on behalf of 13-1011-EL-BNR | 12 |