07/17/2015
|
Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. |
06/04/2015
|
Construction Notice stating that the West Bellaire-Brues 138 kV Line was completed on October 24, 2014 electronically filed by Mr. Ajay K. Kumar on behalf of AEP Ohio Transmission Company. |
06/03/2013
|
Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. |
04/29/2013
|
In the matter of the letter of Notification -Construction Notification West Bellaire-Brues 138 kV (Stringing Second Line) electronically filed by Erin C Miller on behalf of 13-1011-EL-BNR |