Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
03/18/2015 | Notice that Construction on this project was completed on approximately April 25, 2012. | 1 |
04/23/2012 | Notice by FirstEnergy Service Company in regard to Chrysler-Levis Construction project that construction will begin the week of April 23, 2012 filed by John T. Toth. | 1 |
04/10/2012 | Staff investigation report and recommendation field by PUCO Staff. | 1 |
03/08/2012 | In the matter of the application of Construction Notice Chrysler-Lewis Park 138 kV tap to Five Point Substation Pole Relocation as State Route 25 and Five Point Road. | 23 |