CASE NUMBER: 12-0880-EL-BNR
CASE DESCRIPTION: CHRYSLER-LEVIS PARK 138 KV TAP TO FIVE POINT SUBSTATION POLE RELOCATION AT STATE ROUTE 25 AND FIVE POINT ROAD
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
03/18/2015 Notice that Construction on this project was completed on approximately April 25, 2012.
04/23/2012 Notice by FirstEnergy Service Company in regard to Chrysler-Levis Construction project that construction will begin the week of April 23, 2012 filed by John T. Toth.
04/10/2012 Staff investigation report and recommendation field by PUCO Staff.
03/08/2012 In the matter of the application of Construction Notice Chrysler-Lewis Park 138 kV tap to Five Point Substation Pole Relocation as State Route 25 and Five Point Road.