03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
07/02/2013 | Notice that Construction is Complete (Poston-Harrison 138 kV Line) electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc. | 2 |
01/30/2012 | Letter of Notification Poston-Harrison 138 kV Line electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 2 |
11/23/2011 | Staff Investigative Report and Recommendation concerning social and environmental impact of AEP construction project filed by J. Pawley on behalf of the PUCO staff. | 1 |
10/19/2011 | In the matter of the letter of Notification Construction Notice for Poston-Harrison 138k V line (Service to South Central Power Company's Buena Vista Distribution Station) electronically filed by Erin C Miller on behalf of American Electric Power | 10 |