CASE NUMBER: 11-5513-EL-BNR
CASE DESCRIPTION: POSTON/HARRISON 138KV LINE
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
07/02/2013 Notice that Construction is Complete (Poston-Harrison 138 kV Line) electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc.
01/30/2012 Letter of Notification Poston-Harrison 138 kV Line electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc.
11/23/2011 Staff Investigative Report and Recommendation concerning social and environmental impact of AEP construction project filed by J. Pawley on behalf of the PUCO staff.
10/19/2011 In the matter of the letter of Notification Construction Notice for Poston-Harrison 138k V line (Service to South Central Power Company's Buena Vista Distribution Station) electronically filed by Erin C Miller on behalf of American Electric Power