03/24/2015 | Memo closing case with an effective date of 3/24/15. | 1 |
12/17/2013 | Response regarding the status of the 138kV BP Husky Substation filed by J. O'Dell, OPSB. | 1 |
07/27/2010 | Notice of withdrawal and substitution of counsel filed by Staff. | 2 |
06/08/2010 | Letter regarding the City of Oregon Site Plan and zoning permit for the BP-Husky Refining Substation project filed by D. Penner. | 2 |
05/13/2010 | Notice that construction on the BP-Husky Refinery project is expected to begin on or about May 17, 2010 filed by D. Penner, project manager. | 1 |
04/26/2010 | Letter asking that staff be informed of significant progress of site activities and notify the Board when construction is complete filed by Staff. | 1 |
03/23/2010 | Service Notice | 3 |
03/22/2010 | Opinion and order stating that the stipulation be approved and adopted; that a certificate be issued to BP-Husky for the construction, operation, and maintenance of the project, as proposed, at the preferred site; that the certificate contain the 18 conditions set forth in Section V of this opinion and order. (OPSB) | 22 |
02/10/2010 | Transcript of BP Husky Refining, LLC for hearing held on 01/27/10 before Rebecca Hussey, Hearing Examiner,at the Public Utilities Commission of Ohio, 180 East Broad Street, Room 11-C, Columbus, Ohio at 10:00 a.m. electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Sloas, Valerie J. Mrs. | 13 |
02/09/2010 | Transcript for hearing held January 21, 2010 before Administrative Law Judge Rebecca L. Hussey at Oregon Municipal Complex in Oregon, Ohio. . | 10 |
01/26/2010 | Notice of ATSI that they have no objection to the stipulation or to the terms and conditions of the stipulation, filed by M. Parke. | 2 |
01/26/2010 | Joint stipulation and recommended findings of fact and conclusions of law, filed by A. Hammerstein and M. Malone on behalf of PUCO Staff, and K. Boehm on behalf of BP-Husky Refining LLC. | 18 |
01/14/2010 | Proof of publication, filed by K. Boehm on behalf of BP-Husky Refining, LLC. (Lucas County) | 2 |
01/12/2010 | Letter stating that both the preferred and alternate sites of the proposed facility are wholly contained within a facility owned by the applicant filed by K. Boehm on behalf of the applicant. | 1 |
01/05/2010 | Service notice. | 6 |