Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
08/11/2010 | Letter stating that the project of Brookside-Cloverdale 138 kV Transmission Line Reconductoring was completed on approximately June 7, 2010 filed by S. Humphrys on behalf of FirstEnergy Service Company. | 1 |
05/05/2009 | Letter notifying that construction of Brookside-Cloverdale 138 kV Transmission Line Reconductoring Project is expected to begin on or shortly after May 4, 2009 filed by S. Humphrys on behalf of FirstEnergy Service Company. | 1 |
04/20/2009 | Staff report and recommendation for Brookside-Cloverdale 138 kV Transmission Line Reconductoring Project. | 1 |
02/23/2009 | In the matter of the letter of notification, Brookside-Cloverdale 138 kV Transmission Line Reconductoring. | 27 |