03/20/2015
|
Case Action Form to Close Cases effective 3/20/2015. |
08/11/2010
|
Letter stating that the project of Brookside-Cloverdale 138 kV Transmission Line Reconductoring was completed on approximately June 7, 2010 filed by S. Humphrys on behalf of FirstEnergy Service Company. |
05/05/2009
|
Letter notifying that construction of Brookside-Cloverdale 138 kV Transmission Line Reconductoring Project is expected to begin on or shortly after May 4, 2009 filed by S. Humphrys on behalf of FirstEnergy Service Company. |
04/20/2009
|
Staff report and recommendation for Brookside-Cloverdale 138 kV Transmission Line Reconductoring Project. |
02/23/2009
|
In the matter of the letter of notification, Brookside-Cloverdale 138 kV Transmission Line Reconductoring. |