DIS - Case Record for 09-0068-RR-FED Skip to main content

Case Record For:

09-0068-RR-FED

File a Public Comment
Case Title: IN THE MATTER OF THE AUTHORIZATION OF THE INDIANA & OHIO RAILWAY TO INSTALL ACTIVE GRADE CROSSING WARNING DEVICES IN CHAMPAIGN AND WARREN COUNTIES
Status: CL-CLOSED
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 1/28/2009
Date Closed: 2/3/2010
Printable Docket Card Service List
View All
1 - 15 of 23 documents 1 /  2 
Date FiledSummaryPages
02/04/2010Letter stating that the construction and installation of the crossing improvement projects for West Main Street, Warren County, DOT# 525235M, PID No. 85628 and CR 79 Thackery Road, Champaign County, DOT# 258740V PID No. 85632 have been completed and the crossings have been put in service filed by C. Stone on behalf of Indiana & Ohio Railroad. (FAX)1
02/03/2010Case action form closing case with an effective date of 2/3/2010.1
01/22/2010Notification that the construction and installation of the crossing improvement projects will be completed on the following dates, West Main Street-Warren County- DOT#525235M scheduled construction completion date: January 29, 2010 and CR79 (Thackery Road)- Champaign County- DOT# 258740V scheduled construction completion date: January 28, 2010. Filed by C. Stone on behalf of Indiana & Ohio Railroad. (FAX)1
01/08/2010Notification to the PUCO and ORDC that the crossing improvement projects are scheduled to commence construction, W. Main Street on 1/18/2010 and Thackery Road on 1/15/2010 filed on behalf of Indiana & Ohio Railway by C. Stone. (FAX)2
11/24/2009Service Notice2
11/24/2009Entry ordering that I & O request for an extension of time be denied; I & O proceed with and complete the project by February 4, 2010.2
11/13/2009Memo from Staff recommending the Commission deny the request for an extension of time to complete the project, and hold IORY to the previously ordered date filed by G. Martin, Rail Division.2
11/12/2009Request for an extension of time filed by C. Stone on behalf of Indiana & Ohio Railway.2
11/12/2009Service notice.2
11/12/2009Entry ordering I&O's request to suspend the Commission's February 4, 2009 entry be denied; I&O proceed with and complete the projects by February 4, 2010.3
11/12/2009Letter stating work can be completed at anytime filed by K. Seiler on behalf of the City of Marion.13
10/29/2009Memo recommending that the Commission deny IORY's request and reaffirm the construction deadline previously imposed filed by G. Martin on behalf of the Public Utilities Commission of Ohio.3
10/15/2009Letter in response to the I&O's General Director Engineering, Charles A. Stone's letter of October 1, 2009 filed by A. Klodell on behalf of ORDC.13
10/06/2009Request for suspension of PUCO order for construction projects filed by C. Stone on behalf of Indiana & Ohio Railroad. (original)1
10/05/2009Request for suspension of the PUCO order on construction projects filed by C. Stone on behalf of the Indiana & Ohio Railroad. (FAX)1
 
1 /  2 
      
      
Attorney General:
Attorney Examiner: