Date Filed | Summary | Pages |
02/04/2010 | Letter stating that the construction and installation of the crossing improvement projects for West Main Street, Warren County, DOT# 525235M, PID No. 85628 and CR 79 Thackery Road, Champaign County, DOT# 258740V PID No. 85632 have been completed and the crossings have been put in service filed by C. Stone on behalf of Indiana & Ohio Railroad. (FAX) | 1 |
02/03/2010 | Case action form closing case with an effective date of 2/3/2010. | 1 |
01/22/2010 | Notification that the construction and installation of the crossing improvement projects will be completed on the following dates, West Main Street-Warren County- DOT#525235M scheduled construction completion date: January 29, 2010 and CR79 (Thackery Road)- Champaign County- DOT# 258740V scheduled construction completion date: January 28, 2010. Filed by C. Stone on behalf of Indiana & Ohio Railroad. (FAX) | 1 |
01/08/2010 | Notification to the PUCO and ORDC that the crossing improvement projects are scheduled to commence construction, W. Main Street on 1/18/2010 and Thackery Road on 1/15/2010 filed on behalf of Indiana & Ohio Railway by C. Stone. (FAX) | 2 |
11/24/2009 | Service Notice | 2 |
11/24/2009 | Entry ordering that I & O request for an extension of time be denied; I & O proceed with and complete the project by February 4, 2010. | 2 |
11/13/2009 | Memo from Staff recommending the Commission deny the request for an extension of time to complete the project, and hold IORY to the previously ordered date filed by G. Martin, Rail Division. | 2 |
11/12/2009 | Request for an extension of time filed by C. Stone on behalf of Indiana & Ohio Railway. | 2 |
11/12/2009 | Service notice. | 2 |
11/12/2009 | Entry ordering I&O's request to suspend the Commission's February 4, 2009 entry be denied; I&O proceed with and complete the projects by February 4, 2010. | 3 |
11/12/2009 | Letter stating work can be completed at anytime filed by K. Seiler on behalf of the City of Marion. | 13 |
10/29/2009 | Memo recommending that the Commission deny IORY's request and reaffirm the construction deadline previously imposed filed by G. Martin on behalf of the Public Utilities Commission of Ohio. | 3 |
10/15/2009 | Letter in response to the I&O's General Director Engineering, Charles A. Stone's letter of October 1, 2009 filed by A. Klodell on behalf of ORDC. | 13 |
10/06/2009 | Request for suspension of PUCO order for construction projects filed by C. Stone on behalf of Indiana & Ohio Railroad. (original) | 1 |
10/05/2009 | Request for suspension of the PUCO order on construction projects filed by C. Stone on behalf of the Indiana & Ohio Railroad. (FAX) | 1 |
05/27/2009 | Letter asking to ininstall an active grade crossing warning devices at the subject Rail-Highway filed by C. Stone on behalf of Indiana & Ohio Railroad. (FAX) | 1 |
05/27/2009 | Letter asking to install an active grade crossing warning devices at the subject Rail-Highway At-Grade crossing location filed by C. Stone on behalf of Indiana and Ohio Railroad. (FAX) | 1 |
03/27/2009 | Formal IORY Preliminary Engineering submittal items for the Highway-Rail At-Grade Crossing Improvement Project filed on behalf of Xorail and T. Frank by PUCO Staff. | 10 |
03/25/2009 | Formal IORY preliminary Engineering submittal items in reference to the subject Highway-Rail-At-Grade Crossing Improvement project filed on behalf of Xorail and T. Frank by PUCO Staff. | 16 |
02/12/2009 | Letter in regards to the existing warning device projects filed by S. Kirkland on behalf of ORDC. | 4 |
02/04/2009 | Service Notice | 1 |
02/04/2009 | Entry ordered that I&O submit to the Commission and ORDC site plans and cost estimates for the projects by May 5, 2009; that the project be completed by February 4, 2010. | 3 |
01/28/2009 | In the matter of the authorization of the Indiana & Ohio Railway to install active grade crossing warning devices in Champaign County, near Tremont City, CR 79/Thackery Rd., DOT# 258-740V and Warren County, City of Mason, W. Main St., DOT# 525-235M. | 3 |