Date Filed | Summary | Pages |
01/29/2010 | Response to construction notice, advising that construction on the project was completed on approximately December 2, 2009, filed by J. Toth on behalf of FirstEnergy Service Company. | 1 |
11/24/2008 | Correspondence letter in response to the letter of notification filed on February 27, 2008, and notifying the Commission that this project began on October 13, 2008, filed by J. Toth on behalf of FirstEnergy Service Company. | 1 |
05/08/2008 | Staff investigation report and recommendation filed. | 1 |
04/17/2008 | In the matter of the construction notice for Tangy Transmission Substation Expansion. | 11 |
|