CASE NUMBER: 08-0524-EL-BNR
CASE DESCRIPTION: AMERICAN TRANSMISSION SYSTEMS INC / TANGY TRANSMISSION SUBSTATION EXPANSION
DOCUMENT SIGNED ON: 5/3/2024
DATE OF SERVICE: ________________________________________
01/29/2010 Response to construction notice, advising that construction on the project was completed on approximately December 2, 2009, filed by J. Toth on behalf of FirstEnergy Service Company.
11/24/2008 Correspondence letter in response to the letter of notification filed on February 27, 2008, and notifying the Commission that this project began on October 13, 2008, filed by J. Toth on behalf of FirstEnergy Service Company.
05/08/2008 Staff investigation report and recommendation filed.
04/17/2008 In the matter of the construction notice for Tangy Transmission Substation Expansion.