Date Filed | Summary | Pages |
12/15/2009 | Notice that construction was completed on this project and that Dominion East Ohio will place this last segment into service / commercial operation by no later than Friday, December 18, 2009 filed by S. Bloomfield on behalf of Dominion East Ohio. | 1 |
11/09/2009 | Notice that having completed construction, Dominion East Ohio will place a portion of the Franklin 20 inch pipeline in service on November 9, 2009, as it is needed for operation at this time, filed by S. Bloomfield. | 1 |
06/01/2009 | Letter with the approval/clearance from the Ohio Historical Society for the reroute section at Fraze Road filed by S. Bloomfield on behalf of Dominion East Ohio. | 2 |
05/26/2009 | Letter informing the Ohio Power Siting Board of the Franklin 20 Inch Pipeline Project and identification plan for protection of wetland and riparian areas filed by S. Bloomfield. | 16 |
05/08/2009 | Letter informing the Ohio Power Siting Board in regard to the Franklin 20 Inch Pipeline Project, that a copy of the Ohio Environmental Protection Agency notice of intent was sent to staff filed by S. Bloomfield on behalf of Dominion East Ohio. | 3 |
04/30/2009 | Final Execution Plan for HDD Crossings reflecting compliance with Condition No. 8 of the Opinion and Order and Certificate issued March 23, 2009 filed by S. Bloomfield on behalf of Dominion East Ohio. | 25 |
04/28/2009 | Letter of Dominion East Ohio stating to commence construction of the Franklin 20 inch pipeline project on June 1, 2009 filed by S. Bloomfield. | 1 |
04/28/2009 | Letter of Dominion East Ohio stating that the plan was developed in compliance and approval from PUCO staff filed by S. Bloomfield. | 1 |
04/13/2009 | Letter regarding Certificate Condition No. 4 with update and correction to previously filed document filed by S. Bloomfield on behalf of Dominion East Ohio. | 4 |
04/13/2009 | Letter regarding Certificate Condition No. 7, correcting attachment on previously filed document filed by S. Bloomfield on behalf of Dominion East Ohio. | 4 |
04/13/2009 | Letter correcting attachment on previously filed document filed by S. Bloomfield on behalf of Dominion East Ohio. | 5 |
04/10/2009 | Letter informing the Ohio Power Siting Board that with respect to the Franklin 20 Inch Pipeline Project, on April 3, 2009 by electronic mail: a copy of the Hydrostatic Testing Plan was sent to Staff filed by S. Bloomfield on behalf of Dominion East Ohio. | 5 |
04/10/2009 | Letter informing the Ohio Power Siting Board that with respect to the Franklin 20 Inch Pipeline Project, on March 31, 2009 by electronic mail: a copy of the Executive Plan for HDD Crossings was sent to Staff filed by S. Bloomfield on behalf of Dominion East Ohio. | 23 |
04/10/2009 | Letter informing the Ohio Power Siting Board that with respect to the Franklin 20 Inch Pipeline Project, on April 10, 2009 by electronic mail: a copy of the U.S. Army Corp of Engineers approval letter was sent to Staff filed by S. Bloomfield on behalf of Dominion East Ohio. | 4 |
04/10/2009 | Letter and a copy of the approval from the U.S. Department of the Interior Fish and Wildlife Service regarding Condition 4 of the Opinion and Order and Certificate issued March 23, 2009, filed by S. Bloomfield on behalf of Dominion East Ohio. | 4 |