DIS - Case Record for 08-0289-GA-BTX Skip to main content

Case Record For:

08-0289-GA-BTX

File a Public Comment
Case Title: DOMINION EAST OHIO FRANKLIN 20 INCH PIPELINE PROJECT
Status: AR-Archived
Industry Code: GA-GAS
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 3/24/2008
Date Closed:
Printable Docket Card Service List
View All
1 - 15 of 57 documents 1 /  4 
Date FiledSummaryPages
12/15/2009Notice that construction was completed on this project and that Dominion East Ohio will place this last segment into service / commercial operation by no later than Friday, December 18, 2009 filed by S. Bloomfield on behalf of Dominion East Ohio.1
11/09/2009Notice that having completed construction, Dominion East Ohio will place a portion of the Franklin 20 inch pipeline in service on November 9, 2009, as it is needed for operation at this time, filed by S. Bloomfield.1
06/01/2009Letter with the approval/clearance from the Ohio Historical Society for the reroute section at Fraze Road filed by S. Bloomfield on behalf of Dominion East Ohio.2
05/26/2009Letter informing the Ohio Power Siting Board of the Franklin 20 Inch Pipeline Project and identification plan for protection of wetland and riparian areas filed by S. Bloomfield. 16
05/08/2009Letter informing the Ohio Power Siting Board in regard to the Franklin 20 Inch Pipeline Project, that a copy of the Ohio Environmental Protection Agency notice of intent was sent to staff filed by S. Bloomfield on behalf of Dominion East Ohio.3
04/30/2009Final Execution Plan for HDD Crossings reflecting compliance with Condition No. 8 of the Opinion and Order and Certificate issued March 23, 2009 filed by S. Bloomfield on behalf of Dominion East Ohio.25
04/28/2009Letter of Dominion East Ohio stating to commence construction of the Franklin 20 inch pipeline project on June 1, 2009 filed by S. Bloomfield.1
04/28/2009Letter of Dominion East Ohio stating that the plan was developed in compliance and approval from PUCO staff filed by S. Bloomfield.1
04/13/2009Letter regarding Certificate Condition No. 4 with update and correction to previously filed document filed by S. Bloomfield on behalf of Dominion East Ohio.4
04/13/2009Letter regarding Certificate Condition No. 7, correcting attachment on previously filed document filed by S. Bloomfield on behalf of Dominion East Ohio.4
04/13/2009Letter correcting attachment on previously filed document filed by S. Bloomfield on behalf of Dominion East Ohio.5
04/10/2009Letter informing the Ohio Power Siting Board that with respect to the Franklin 20 Inch Pipeline Project, on April 3, 2009 by electronic mail: a copy of the Hydrostatic Testing Plan was sent to Staff filed by S. Bloomfield on behalf of Dominion East Ohio.5
04/10/2009Letter informing the Ohio Power Siting Board that with respect to the Franklin 20 Inch Pipeline Project, on March 31, 2009 by electronic mail: a copy of the Executive Plan for HDD Crossings was sent to Staff filed by S. Bloomfield on behalf of Dominion East Ohio.23
04/10/2009Letter informing the Ohio Power Siting Board that with respect to the Franklin 20 Inch Pipeline Project, on April 10, 2009 by electronic mail: a copy of the U.S. Army Corp of Engineers approval letter was sent to Staff filed by S. Bloomfield on behalf of Dominion East Ohio.4
04/10/2009Letter and a copy of the approval from the U.S. Department of the Interior Fish and Wildlife Service regarding Condition 4 of the Opinion and Order and Certificate issued March 23, 2009, filed by S. Bloomfield on behalf of Dominion East Ohio.4
 
1 /  4 
      
      
Attorney General:
Margard, Werner
Attorney Examiner:
Price, Gregory