Date Filed | Summary | Pages |
06/12/2006 | Letter stating that this project was completed on June 1, 2006 filed by T. Krauss on behalf of FirstEnergy Service Company. | 1 |
10/17/2005 | Letter in response to the letter of notification and informing that construction would begin on approximately October 17, 2005; that the Commission will be notified once the project is completed filed by T. Krauss on behalf of FirstEnergy Service Company. | 1 |
05/10/2005 | Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss. | 3 |
01/06/2005 | Staff Investigation report and recommendation filed by PUCO staff. | 1 |
12/06/2004 | In the matter of Letter of Notification of American Transmission Systems, Inc. for Beaver-Brookside 138 kV Transmission Line Tap to Lorain Medina REC's South Nova Substation. | 17 |