DIS - Case Record for 04-1823-EL-BLN Skip to main content
      
      
CASE NUMBER: 04-1823-EL-BLN
CASE DESCRIPTION: AMERICAN TRANSMISSION SYSTEMS, INC.BEAVER - BROOKSIDE 138KV TRANSMISSION LINE TAP
DOCUMENT SIGNED ON: 5/7/2024
DATE OF SERVICE: ________________________________________
06/12/2006 Letter stating that this project was completed on June 1, 2006 filed by T. Krauss on behalf of FirstEnergy Service Company.
10/17/2005 Letter in response to the letter of notification and informing that construction would begin on approximately October 17, 2005; that the Commission will be notified once the project is completed filed by T. Krauss on behalf of FirstEnergy Service Company.
05/10/2005 Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss.
01/06/2005 Staff Investigation report and recommendation filed by PUCO staff.
12/06/2004 In the matter of Letter of Notification of American Transmission Systems, Inc. for Beaver-Brookside 138 kV Transmission Line Tap to Lorain Medina REC's South Nova Substation.