Date Filed | Summary | Pages |
04/18/2005 | Memo stating that grade crossing improvements and/or upgrades ordered have been completed and installed and request that the Docketing Division close cases of record, filed on behalf of PUCO Staff-Railroad Section. | 1 |
06/30/2004 | Entry ordered that; NS submit to the Commission and ORDC site plans and cost estimates for the projects by 9/30/04, that by 10/07/04, NS file a letter advising that is has submitted site plans and cost estimates to the Commission and ORDC; that projects to be completed by 6/30/2005; that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization; that NS notify the Commission and ORDC 30 days before the projected date of completion. | 3 |
06/30/2004 | Service Notice | 2 |
06/16/2004 | In the matter of the authorization of Norfolk Southern Railway to construct active grade crossing warning devices in Gallia, Hancock, Fairfield and Athens Counties. | 3 |
|